Work is underway on the
Avondale and Point Hayden Waterline Project!
NKWD awarded the
project to MDM Construction out of Hayden, Idaho.
The Contractor began construction on Point Hayden the week of August
23. Expect road
closures (for through traffic) during main line construction over
the next two to three weeks. Also expect to encounter rough
road conditions in these areas until such time as the roadway
restoration is completed.
The Contractor began construction on Avondale Lane and Avondale Loop the
week of July 12 and has begun installation of the water main working
north. Expect road closures (for through traffic) during main line
construction over approximately the next month. Also expect to
encounter rough road conditions in these areas until such time as the
roadway restoration is completed.
The following is the tentative construction schedule for the
project:
· Merman,
Kensington, Trafalgar, Avon Circle, Strahorn:
Main line: Complete
Services: Complete
Roadway: Complete
Final Clean-up: August 24 to September 7
· 09/02/10 Update:
Avondale Area:
Mainline installation along Avondale Lane, Avondale Loop,
Brighton Court and Thames Court is complete. The mainline will now be
flushed and tested (pressure and bacteria). Service installation is
complete for Avondale Lane and is proceeding north along Avondale Loop.
As of this morning, service installation was complete to approximately
2000 feet north of Avondale Lane (near 11719 N. Avondale Loop).
Road work on Avondale Lane is underway. Base rock has been
installed for the length of Avondale Lane. Excavation and base rock
installation began approximately 1300 feet north of Avondale Lane (near
11491 N. Avondale Loop) working south towards Avondale Lane today. The
Contractor expects to complete approximately 600 feet of excavation and
base rock installation every two days.
The main roadway along Merman, Kensington, Trafalgar and Avon Circle
has been paved. Final cleanup of this area is scheduled to be complete
next week.
Kensington is now open to through traffic.
No work will occur on Monday, September 6.
Point Hayden Area:
Mainline installation began at the intersection of Point
Hayden West and Point Hayden East and is proceeding along Point Hayden
West toward Lake Forest Drive. As of this morning, approximately 1,000
feet of mainline was installed.
No work will occur on Monday, September 6.
We will update this site as we have more information available.
· Avondale
Loop, Lane, Brighton, Thames
Main line: July 15 through August 31
Services: August 12 through September 10
Roadway: August 25 through September 22
Final Clean-up: September 29 through October 13
· Point
Hayden
Main line: August 25 through September 22
Services: September 22 through October 6
Roadway: October 6 through October 25
Final Clean-up: October 25 through November 3
· Construction
Completion:
November 14
Please check back frequently for updates to this schedule and
should you have any
questions, please feel free to contact us.
The Contractor is working hard to complete this work on schedule.
We recognize the
inconvenience to the residents and thank you in advance for your
patience.